Water Treatment Plant

Construction of the WTP at 7055 Boonesboro Road adjacent to the Lower Howards Creek Wastewater Treatment Plant was initiated on March 5, 2018.  This project was designed and coordinated in conjunction with the 24-inch Raw and Finished Water Main Project (completed) as well as the Raw Water Intake improvements project (completed).  The preliminary engineering work developed six (6) Technical Memorandums establishing direction for design of the new treatment facilities.  Bell Engineering is serving as the Engineer of Record.  WMU has plans to continue to utilize the Carroll Ecton Reservoir as a back-up/secondary water supply and construct a raw water transfer pumping station at the existing water treatment plant in accord with construction of the new water treatment plant facilities.  All official approval documentation from KDOW has been received.  A preconstruction meeting was held on January 24, 2018 and the official sale of bonds has been completed establishing the remaining financing of the project.  The first progress meeting and an official groundbreaking ceremony was held on March 15, 2018.  The next monthly progress meeting is scheduled for Thursday, December 13, 2018.  Work continues in the filter building, high service pump (clearwell) and chemical building areas.   Approximately 30% of the project time has expired prior to substantial completion.  Contractor payments show approximately 12% paid out for work completed through Pay Request No. 8.  As of the end of October 2018 the contractor is 21% complete with construction.  As of this time the project remains on schedule.  The following schedule outlines milestones for the project achieved and moving forward.

  • Design completion – 6/30/17
  • Solicitation of Construction Bids – 7/19/17
  • Construction Bid Opening – 10/27/17
  • Construction Bid Award – 12/7/17
  • Authorization for City to Issue Bonds – 12/7/17
  • First Reading of Bond Ordinance – 12/19/17
  • Second Reading of Bond Ordinance – 1/2/18
  • Bond Sale – 2/1/18
  • Bond Closing – 2/15/18
  • Notice to Proceed – 3/5/18
  • Construction Begins – 3/5/18
  • Groundbreaking – 3/15/18
  • Substantial Completion – 3/5/20