Current and Completed Project Snapshot

 

                  Project                               Status           Completion Date         Cost to date                        

New Water Treatment Plant

Design/Bid

10-30-16

N/A

Hampton Manor Sanitary Sewer Improvements

Construction

7-31-19

$1,250,700 (as-bid)

West Hickman Street System Improvements

Complete

8-31-17

$183,243.89

Winchester Bypass (Veterans Memorial Parkway) Utility Relocations

Design

N/A

N/A

Short Street Sewer Improvements

Construction

10-6-17

$90,000 (estimate)

Bonnie Brook Lane Water Line Improvements

Design/Construction

10-31-17

(anticipated)

$25,000 (estimate)

Fire Hydrant Painting 2017

Complete

8-17-17

$19,187.20

Fulton Road Sewer Line Relocation

Design (City project)

N/A

N/A

Elevated Pressure Zone #3

Preliminary Design

12-1-16 (Preliminary Design)

$422,000.00 (construction in-house estimate)

Kentucky River Raw Water Pump Station Upgrades

Complete

1-5-17

$1,225,133.64

Maple Street Sewer Replacement (Joint Project – City )

Complete

11-17-16

$536,765.03 (total project bid)