Current and Completed Project Snapshot

 

             Project                               Status           Completion Date         Cost to date                        

New Water Treatment Plant

Design

9-1-16

N/A

Elevated Pressure Zone #3

Preliminary Design

12-1-16 (Preliminary Design)

$422,000.00 (construction in-house estimate)

Fulton Road Sewer Line Relocation

Design (City project)

N/A

N/A

Hampton Manor Sanitary Sewer Improvements

Construction

7-31-19

$1,250,700 (estimate)

West Hickman Street System Improvements

Construction

6-30-17

$215,306.03 (estimate)

Winchester Bypass (Veterans Memorial Parkway) Utility Relocations

Design

N/A

N/A

Short Street Sewer Improvements

Design/Construction

N/A

$90,000

Kentucky River Raw Water Pump Station Upgrades

Complete

1-5-17

$1,225,133.64

Maple Street Sewer Replacement (Joint Project – City )

Complete

11-17-16

$536,765.03 (total project bid)

Fire Hydrant Painting (Contract No. 80)

Complete

8-18-16

$19,311.00

Crawford Avenue Water Improvements

Complete

4-30-16

$59,461.00